PROPOSED PROJECT TIMELINE

November 2022
Hawaiian Electric

Ongoing
Community Outreach and Community Benefits Outreach

August 2023
Project Selection by Hawaiian Electric Company

March 2024
Community Outreach meeting

May 2024
Power Purchase Agreement filed with Hawai‘i Public Utilities Commission

October 2024
Second Community Outreach Meeting

Q2 2024
Environmental Studies Completed

Q2 2024
Permitting Completed

Q4 2024
Construction

Q4 2027
Commercial Operations

Q1 2027
Community Benefits Program Launch

2027 for 30 years
Community Benefits Program Annual Donation

30 years
Power Purchase Agreement Term

End of Term
Decommissioning