PROPOSED PROJECT TIMELINE
November 2022
Hawaiian Electric
Ongoing
Community Outreach and Community Benefits Outreach
August 2023
Project Selection by Hawaiian Electric Company
March 2024
Community Outreach meeting
May 2024
Power Purchase Agreement filed with Hawai‘i Public Utilities Commission
October 2024
Second Community Outreach Meeting
Q2 2024
Environmental Studies Completed
Q2 2024
Permitting Completed
Q4 2024
Construction
Q4 2027
Commercial Operations
Q1 2027
Community Benefits Program Launch
2027 for 30 years
Community Benefits Program Annual Donation
30 years
Power Purchase Agreement Term
End of Term
Decommissioning